[Construction] Deadline Extended but Bond Expired?
Hello, this is Attorney Bae Ki-hyung of Cheongchul Law Firm.
In construction projects, it is very common for the contractor to miss the originally agreed completion deadline because of frequent design changes, bad weather, complaints from neighbors and the like, and for the project owner (the employer) and the contractor to agree to extend the completion deadline.
In such cases, the contractor often forgets to renew the term of the 'performance bond' or 'advance payment bond' it obtained and submitted when the contract was signed, and simply carries on with the work. If the contractor then abandons the site within the extended completion period because of financial difficulties, the owner belatedly claims the bond amount from the surety.
The surety then refuses payment, arguing that "the bond period stated in the bond certificate has already expired, so we bear no liability for a bond event that occurred afterwards." The owner, for its part, protests that "the construction contract period was extended, so surely the bond period was extended as well."
Today, through Supreme Court precedents, we explain clearly whether the surety is liable when a bond event occurs after the completion deadline under the construction contract has been extended but the bond period has not been renewed.
Extension of the Completion Deadline and the Bond Period – When the Surety Is Released for Events After the Bond Period
[Question] The owner and the contractor agreed to extend the construction period. However, no application to extend the bond period was filed with the surety, and the contractor went bankrupt after the original bond period had passed. Can the owner recover the bond amount?
[Answer] To state the conclusion first, as a rule the owner cannot recover the bond amount. This is because an extension of the construction contract period by agreement between the parties does not automatically extend the term of the bond contract.
The Supreme Court strictly separates the principal contract (the construction contract) from the bond contract (a guarantee issued by the Construction Guarantee Cooperative, Seoul Guarantee Insurance or the like). A bond contract is in the nature of 'insurance': in exchange for a bond fee, the surety assumes only the risk arising during a defined period.
1. The Rule: No Liability for Events After the Bond Period
The Supreme Court has clearly held that "where the bond creditor (the owner) has granted the cooperative member (the contractor) an extension of the performance date to a point after the bond period, unless the Construction Guarantee Cooperative extends the bond period accordingly, this does not mean that the bond period under the Cooperative's bond contract is automatically changed to match" (Supreme Court Decision 2014Da40220, September 4, 2014; Supreme Court Decision 2002Da59764, August 19, 2005). In other words, if the parties themselves extended the construction deadline so that the postponed date falls after the bond period, then even if the contractor stops work on that postponed date, this is an 'event occurring after the agreed bond period,' and the surety has no obligation to pay the bond amount.
2. Exception 1: Where the Extension Was Granted After the Deadline Had Already Passed
There is, however, an exception that can rescue the owner. It turns on the question of 'when' the extension was granted. If the completion deadline was not extended in advance, but rather the completion deadline (that is, a date within the bond period) arrived while the contractor had still not completed the work, and only afterwards did the owner grant an extension of the completion deadline, the conclusion changes. The Supreme Court held in such a case that "the mere fact that the completion deadline was extended to a point after the insurance period does not mean that no insured event occurred within the insurance period" (Supreme Court Decision 2009Da41366, March 11, 2010). In other words, because a default (bond event) in the form of 'failure to complete within the deadline' had already definitively occurred within the original bond period, the surety cannot escape liability even though more time was granted afterwards. Even in this case, however, whether a bond event has actually occurred depends on whether forfeiture of the contract bond under the principal contract requires only a default or also requires termination, so the principal contract and the bond terms and conditions must be reviewed together.
3. Exception 2: Special Provisions in the Terms and Conditions
The wording of the bond's terms and conditions must also be examined. If the bond terms contain a special statement to the effect that "this bond remains in force until the actual completion date of the work notwithstanding the expiry of the bond period," the Supreme Court has held that there is room to interpret this as the surety's expression of intent to pay the bond amount regardless of the bond period, even where the event occurred after the bond period had passed because of delays in the work (Supreme Court Decision 96Da2453, June 28, 1996).
Always Obtain a Bond Period Extension Endorsement When Extending the Completion Deadline
For the owner (employer), avoiding this fatal mistake is critical. When agreeing with the contractor to extend the completion deadline because of delays (a contract amendment), do not simply sign the amended contract; it is essential to require the contractor, before the expiry date of the existing bond, to pay the additional fee to the surety and obtain and submit a 'new bond (endorsement) with an extended bond period'. Note also that a claim on a Construction Guarantee Cooperative bond is extinguished by prescription unless exercised within two years from the expiry date of the bond period (Framework Act on the Construction Industry Article 67(4) (건설산업기본법 제67조 제4항)), and that surety insurance is subject to the limitation period for insurance claims (Commercial Act Article 662 (상법 제662조), three years), so the deadline for making a claim keeps running even while the prospects of recovery are being assessed.
Conversely, from the standpoint of the surety or the contractor, if the surety did not consent to or was unaware of the extension of the principal contract, it should actively raise the defense that the bond period has expired and resist an unwarranted payment of the bond amount.
Because the question of the order in which the bond period extension and the bond event occurred involves complex facts, such as the timing of the parties' agreement and the interpretation of the specific wording of the bond terms, a concrete legal review is needed from the earliest stage after the event.
Drawing on its extensive practical experience in a wide range of construction bond disputes and its deep understanding of the interpretation of terms and conditions, Cheongchul Law Firm protects owners at risk of unfairly losing their bond recovery and provides optimal solutions for resolving such disputes. If you are facing difficulties with a bond claim because the bond period has expired or renewal was missed, please consult the experts at Cheongchul Law Firm.
-------
Attorney Bae Ki-hyung has worked at the Defense Installations Agency and in the construction and real estate team of a major law firm, providing legal advice on every stage of government contracts and construction projects, including large-scale construction works such as public works, defense facility projects and SOC infrastructure projects, and resolving related litigation. With this rich experience and expertise, Attorney Bae welcomes inquiries at any time on matters involving public works, private construction projects, public procurement contracts, and state, local-government and other public property.
* * *
Cheongchul Law Firm is composed solely of attorneys with backgrounds at Korea's five largest law firms, the prosecutors' office and the legal departments of major corporations. Rather than a single attorney, a team of specialists in the fields relevant to each matter works together to respond. Going beyond resolving isolated issues, Cheongchul provides comprehensive solutions across the client's business, focusing its legal consulting on ultimately achieving what the client wants. If you need help reaching your goals, please do not hesitate to contact Cheongchul.
Related work cases that are good to see together
More Articles in This Practice Area
Browse by practice area
서울 강남구 테헤란로 403 리치타워 7층
Tel. 02-6959-9936
Fax. 02-6959-9967
cheongchul@cheongchul.com
개인정보처리방침
면책공고
© 2025. Cheongchul. All rights reserved
![[건설분쟁 변호사] 준공기한 연장하면 보증서 효력도 자동 연장될까? (보증기간 경과 후 사고) - 계약이행보증서 보증기간 미갱신, 보증기관 면책 원칙과 예외, 보증기간 연장 배서, 보증금 청구권 소멸시효](https://framerusercontent.com/images/d3VeTS5GIkknUn9RKJrHJarIKpw.png?width=1080&height=675)