[건설분쟁 변호사] 보증 한도액을 초과한 지연손해금, 보증기관에 청구할 수 있을까? 보증채무 이행지체 지연손해금 대법원 2013다76567 판결

[Construction] Delay Interest Beyond the Bond Limit

[Construction] Delay Interest Beyond the Bond Limit

[Construction] Delay Interest Beyond the Bond Limit

Hello, this is Attorney Bae Ki-hyung of Cheongchul Law Firm.

When a contractor goes bankrupt or defaults on a construction project, the project owner (the employer) claims the performance bond or the advance payment refund bond from a guarantee institution such as the Korea Construction Guarantee Cooperative or Seoul Guarantee Insurance in order to cover its losses.

In practice, however, guarantee institutions often put off paying out the bond for months or even years, citing on-site investigations or reviews of who is responsible. The owner suffers a substantial interest loss for every day the payout is delayed. What happens if the principal and interest the contractor owes have already reached the "guarantee limit" stated in the bond? Whether the delay interest caused by the guarantor's own late payment can be recovered separately, over and above the guarantee limit, is an important practical issue.

In this post, I explain the Supreme Court's standard on whether delay interest can be claimed in excess of the guarantee limit when a guarantee institution delays paying out the bond.

Delay Interest Owed by the Guarantor – The Scope Borne Separately from the Guarantee Limit

[Question] The guarantee limit stated in the bond is KRW 1 billion, and the loss caused by the contractor's default has already reached KRW 1 billion. Yet the guarantee institution has put off payment for a year after receiving the claim. Can the owner claim from the guarantee institution, in addition to the KRW 1 billion guarantee limit, 'delay interest for the one-year delay in payment'?

[Answer] In short, yes, you can. Even if the loss from the contractor's default has already exhausted the guarantee limit, where the guarantee institution itself put off payment, 'delay interest arising from the guarantor's own delay in performing the guarantee obligation' can be claimed and recovered separately from the guarantee limit.

On the relationship between the guarantee amount limit in the bond and delay interest, the Supreme Court held as follows in Supreme Court Decision 2013Da76567 (Feb. 27, 2014).

1. The Meaning of the Guarantee Limit (The Ceiling of the Principal Obligation)

In general, the guarantee amount stated in a bond sets the ceiling on the 'contractor's (principal debtor's) obligation' for which the guarantee institution is liable. Therefore, this limit covers not only the principal the contractor must repay to the owner but also the interest and delay interest caused by the contractor's fault, and as a rule the total cannot exceed the guarantee limit.

2. The Guarantor's Own Delay in Performance (Calculated Separately from the Limit)

However, the Supreme Court held that "because the guarantee obligation is a separate obligation from the principal obligation, delay interest arising from the delay in performing the guarantee obligation itself must be borne separately from the guarantee limit." If the owner duly claimed the bond and the due date (time for performance) has passed, yet the guarantee institution delayed performance, the delay interest for that period results not from the contractor's debt but from the 'guarantee institution's own default,' so it must be paid in addition, free from the restriction of the guarantee limit.

3. The Applicable Rate of Delay Interest (Points to Note)

In practice, care is needed as to which interest rate applies when claiming delay interest. The Supreme Court decision above held that "absent a special agreement on the default interest rate for the guarantee obligation, the statutory rate under the Commercial Act or the Civil Act applies according to the nature of the transaction, and the default rate agreed for the principal obligation does not automatically apply." For example, even if the construction contract between the owner and the contractor provides that "interest at 15% per annum shall be added upon refund of the advance payment," if the guarantee terms do not separately set the guarantor's default rate, the guarantor's liability for delay is subject not to 15% per annum but to the statutory commercial rate of 6% per annum. In the actual case before the Court, the bond stated that 'the guarantee amount of this bond includes agreed interest at 7% per annum,' but the Supreme Court viewed this as merely defining the scope of the guarantee liability, not as an agreement on the default rate for the guarantee obligation.

Key Check – Pin Down When the Bond Payment Deadline Passed and Claim Delay Interest

In the end, when a guarantee institution keeps putting off payment on the pretext of review, the owner (employer) should not stop at mere reminders.

First, check the guarantee terms to determine the 'bond payment deadline (typically within a set number of days after the investigation following the claim is completed)', and from the moment that deadline passes, give notice by certified mail or similar means that delay interest is accruing regardless of the guarantee limit, and demand prompt performance. If the matter proceeds to litigation, the strategy should be to strictly hold the guarantor liable for its own delay in performing the guarantee obligation, in addition to the principal (the guarantee limit), so that the delay interest is recovered in full. Where the claim is brought in court, a rate of 12% per annum may apply from the day after the copy of the complaint is served on the guarantee institution under the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings (소송촉진 등에 관한 특례법) (Article 3(1) of the Act). However, this does not apply to the extent it is deemed reasonable for the guarantee institution to dispute the existence or scope of its obligation (Article 3(2)). In addition, a claim for the bond amount against the Construction Guarantee Cooperative is extinguished by prescription if not exercised within two years from the expiry date of the guarantee period (Article 67(4) of the Framework Act on the Construction Industry (건설산업기본법)), so the owner must take care not to let this deadline pass while negotiations with the guarantee institution drag on.

Conversely, a guarantee institution that cannot prove a legitimate reason for its delayed review or refusal to pay may end up bearing unexpected delay interest exceeding the limit, so it is important to make a prompt legal assessment from the early stage of receiving the claim.

Litigation over bond claims requires careful legal analysis, including interpretation of the guarantee terms, distinguishing the principal obligation from the guarantee obligation, and fixing the start date for delay interest. If you are facing a dispute over bond payouts and delay interest worth billions of won, please consult the experts at Cheongchul Law Firm, who are well versed in construction guarantee practice.

-------

Attorney Bae Ki-hyung has worked at the Defense Installations Agency and in the construction and real estate team of a major law firm, providing legal advice on the entire process of government contracts and construction projects, including large-scale construction works such as public works, defense facility projects, and SOC construction projects, and has extensive experience and proven skill in resolving related disputes. If you need assistance with public works, private construction projects, public procurement contracts, state property, local government property, or public property, please feel free to contact us at any time.

* * *

Cheongchul Law Firm is composed exclusively of attorneys from Korea's top five law firms, the prosecution service, and the in-house legal teams of major corporations, and responds to each matter with a team of specialists in the relevant fields rather than a single attorney. Going beyond resolving specific issues, Cheongchul provides comprehensive solutions for the business as a whole, focusing on legal consulting that ultimately achieves what the client wants. If you need help achieving your goals, please do not hesitate to contact Cheongchul.

Related work cases that are good to see together

법무법인 청출 로고
법무법인 청출 로고
법무법인 청출

서울 강남구 테헤란로 403 리치타워 7층

Tel. 02-6959-9936

Fax. 02-6959-9967

cheongchul@cheongchul.com

개인정보처리방침

면책공고

© 2025. Cheongchul. All rights reserved

상담
신청
전화 상담 · 평일 09:00~18:0002-6959-9936
전화상담 상담 신청